Actions
Activity #1287
closedModule #882: Hands on & Code Familiarization
Hands on & Code Familiarization - Initial Setup - Week 4
Start date:
10/02/2023
Due date:
10/06/2023
% Done:
100%
Estimated time:
Planned Due Date:
Description
04/10/2023
----------
1) Attended team meeting conducted by Devanand Sir
Points Discussed
================
1. Screen designing of withdrawal benefit
2. Assign Sreeshna to explore about the withdrawal benefit covered in the training sessions and to prepare a document based on it.
3. Design the withdrawal benefit proto by 11/010/2023 and db design
4. Send the designed page to Thara and Devanand Sir for verification and to present the same to CDAC Pune on 13/10/2023.
5. Check whether the demo application is responsive.
2) Supported the team members in fixing errors in the demo application code - In progress
05/10/2023
----------
Supported the team members in fixing errors in the demo application code - Completed the UAN Search & Listing
06/10/2023
----------
Sample design document send to the team and explained how to prepare the design document.
Supported the team members in validation works in the demo application code.