Activity #1054
Updated by Nisha Balakrishnan almost 3 years ago
12/09/2024
1.Attended meeting conducted by Devanand Sir and got new responsibility as the PL of the EPFO project.
2.Prepared a document regarding the points discussed in the training sessions conducted by Ranjit Raman Sir.
13/09/2024
1.Assigned tasks to Ashitha in Redmine that has been shared by Devanand Sir in google sheets.
14/09/2024
1.Assigned tasks to Rasmiya in Redmine that has been shared by Devanand Sir in google sheets.
2.Communicated with CDAC Pune team via phone and email for getting Git access for 3 team members.
3.Supported CDAC Pune in accessing Ashitha’s PC using Any desk for setting git access for 3 team members.The tvm team remotely connected with Pune office pc to do the configuration - Problem not
solved.
4.Reported issues in Field Office and Member Portal to CDAC Pune Team via mail.For Member Portal-They shared an image folder to correct the issue - issue not solved
5.Field Office-They reported to remove the duplicate java files from the project - In progress
15/09/2024
1.For fixing Member Portal Issue - Ankit Pune remotely connected to Ashitha's PC using Anydesk and resolved the issue.He created user credentials using Ashitha’s Aadhar details and created a new user.
2.Supported CDAC Pune in accessing Rasmiya’s PC using Any desk for setting access for 3 team members in Git repository - Issue resolved and all 3 members got git access.
3.Supported team members in identifying the menu (source code) in the demo application.