50 BMI Feature New High Study,Design and development of Blink tracking algorithm Asha SA 11/17/2022 12/01/2022 10:15 AM Actions
49 BMI Activity New Urgent Explore Blink tracking algorithms Asha SA 11/17/2022 11/17/2022 01:18 PM Actions
48 BMI Feature New Normal Design and Development of Matlab based SSVEP data collection tool Asha SA 11/17/2022 11/17/2022 01:17 PM Actions
47 BMI Activity New Normal Design and development of Matlab based SSVEP tool for data collection 11/17/2022 11/17/2022 01:15 PM Actions
46 Digitally Connected Tribal Colonies -II Activity New Normal Letter for Server at State Data Centre Binu Janardhanan Activity #7 11/15/2022 11/30/2022 05/03/2023 02:16 PM Actions
45 Digitally Connected Tribal Colonies -II Activity New Normal Letter to IT Mission Director fo K FON connection Binu Janardhanan Activity #7 11/15/2022 11/30/2022 01/12/2023 05:13 PM Actions
44 Digitally Connected Tribal Colonies -II Activity New Normal Letter to IT Mission from STDD for VC software Binu Janardhanan Activity #7 11/15/2022 11/30/2022 01/12/2023 05:12 PM Actions
43 BMI Feature New Normal Eye blink detection algorithm in python Rashmi Sinha 11/18/2022 10/06/2023 07/19/2023 01:49 PM Actions
42 Digitally Connected Tribal Colonies -II Activity New Normal Recruitment of Nurses Binu Janardhanan Activity #19 11/14/2022 12/30/2022 11/14/2022 04:02 PM Actions
41 Digitally Connected Tribal Colonies -II Activity New Normal Implementation and Support 04/01/2023 12/31/2025 11/14/2022 02:32 PM Actions
40 Digitally Connected Tribal Colonies -II Sub module New Normal Development of e-Learning application for eEducation Support Shameera S L Sub module #16 01/30/2023 03/31/2023 07/25/2025 03:56 PM Actions
39 Digitally Connected Tribal Colonies -II Activity New Immediate Communicate with Amrutha for A-View software for eEducation Binu Janardhanan Activity #7 11/03/2022 11/10/2022 11/28/2022 11:24 AM Actions
38 Digitally Connected Tribal Colonies -II Activity New Normal Prepare SRS of the Network and Hardware Part of the project Arun S Activity #37 11/03/2022 11/30/2022 11/03/2022 04:53 PM Actions
37 Digitally Connected Tribal Colonies -II Activity New Normal Requirement Study Binu Janardhanan 11/01/2022 11/30/2022 11/03/2022 04:53 PM Actions
36 Digitally Connected Tribal Colonies -II Activity New Normal Identify 3 Screening HUB and Studio Room @ Wayanad Binu Janardhanan Activity #7 11/03/2022 11/30/2022 05/03/2023 02:14 PM Actions
35 Digitally Connected Tribal Colonies -II Activity New High Procurement Binu Janardhanan 10/26/2022 11/30/2022 07/07/2023 09:51 AM Actions
34 Digitally Connected Tribal Colonies -II Activity New High Setting up District Project Monitoring Committe Binu Janardhanan Activity #7 11/03/2022 11/30/2022 01/12/2023 05:08 PM Actions
33 Digitally Connected Tribal Colonies -II Activity New High Procurement of UPS for Padanamury and Studio Centre Arun S Activity #35 11/01/2022 11/30/2022 11/03/2022 02:07 PM Actions
32 Digitally Connected Tribal Colonies -II Activity New High Prepare specification of interactive TV for Studio Centre and Normal for Padanamuri (8 Nos) Arun S Activity #35 11/01/2022 11/10/2022 11/03/2022 02:07 PM Actions
31 Digitally Connected Tribal Colonies -II Activity New High Prepare specification of computer & accessories and raise PR for Padanamury Shaji A Activity #35 11/01/2022 11/30/2022 11/03/2022 02:05 PM Actions
29 Digitally Connected Tribal Colonies -II Activity New Immediate Design the network of the DCTC System Arun S Module #27 11/01/2022 11/30/2022 11/03/2022 04:57 PM Actions
28 Digitally Connected Tribal Colonies -II Activity New Normal Prepare DCTC web application system requirement specicifcation Nisha Balakrishnan Activity #37 11/01/2022 11/30/2022 11/03/2022 04:51 PM Actions
27 Digitally Connected Tribal Colonies -II Module Resolved Immediate Design and Development the System Binu Janardhanan 10/27/2022 02/02/2024 10/06/2025 09:49 AM Actions
26 Digitally Connected Tribal Colonies -II Activity New High Procurement of Shelf, chairs and table for the project Arun S Activity #35 11/01/2022 11/30/2022 11/03/2022 02:07 PM Actions
24 BMI Feature New Normal Experiment log preparation Anusree V Feature #4 11/22/2022 07/07/2023 10:13 AM Actions