Activity #1502
closedFeature #63: DigiPatho Web -- Development, Validation, Certification and Deployment
Feature #406: WSI Processing Pipeline
Upload pyramidal tiff to server
Start date:
11/13/2023
Due date:
11/17/2023
% Done:
100%
Estimated time:
Planned Due Date:
07/25/2025
Description
Create folder structure in server attached nas
Run tusd
Upload pyramidal tiff
Updated by Thara S Pillai about 2 years ago
- Assignee changed from Jiji P B to Shameera S L
Updated by Thara S Pillai over 1 year ago
- Assignee changed from Shameera S L to Aswathy M G
Updated by Thara S Pillai about 1 year ago
- % Done changed from 0 to 80
- Planned Due Date set to 05/19/2025
The developed module was tested from remote screening hubs, where files were successfully uploaded to the remote server. However, the rename functionality encountered an error and needs to be debugged and resolved.
Updated by Thara S Pillai about 1 year ago
- Status changed from New to In Progress
Updated by Thara S Pillai about 1 year ago
- Planned Due Date changed from 05/19/2025 to 06/23/2025
Updated by Thara S Pillai about 1 year ago
- Planned Due Date changed from 06/23/2025 to 07/04/2025
Updated by Thara S Pillai about 1 year ago
- Parent task changed from #1500 to #406
Updated by Thara S Pillai about 1 year ago
- Planned Due Date changed from 07/04/2025 to 07/18/2025
Updated by Thara S Pillai about 1 year ago
IIP image server and TUS server maps to a folder location for image access
The developer level testing for image access from WSI viewers pending.
The developer level testing for rendering for resumed uploads also pending.
Updated by Thara S Pillai about 1 year ago
- Planned Due Date changed from 07/18/2025 to 07/25/2025
Updated by Thara S Pillai 8 months ago
- Status changed from In Progress to Closed