Project

General

Profile

Actions

Activity #1263

closed

Module #882: Hands on & Code Familiarization

Hands on & Code Famalirisation - Initial Setup - Week 3

Added by Nisha Balakrishnan almost 3 years ago. Updated over 2 years ago.

Status:
Closed
Priority:
Normal
Category:
-
Start date:
09/25/2023
Due date:
09/29/2023
% Done:

100%

Estimated time:
Planned Due Date:

Description

27/09/2023 & 29/09/2023

Supported the team members in fixing errors in the demo application code
Started initial works of PMP

Actions #1

Updated by Nisha Balakrishnan almost 3 years ago

  • Tracker changed from Module to Activity
Actions #2

Updated by Nisha Balakrishnan almost 3 years ago

  • Subject changed from Hands on & Code Famalirisation - week 3 to Hands on & Code Famalirisation - Initial Setup - Week 3
Actions #3

Updated by Nisha Balakrishnan over 2 years ago

  • Status changed from New to Closed
Actions

Also available in: Atom PDF