Actions
Activity #1263
closedModule #882: Hands on & Code Familiarization
Hands on & Code Famalirisation - Initial Setup - Week 3
Start date:
09/25/2023
Due date:
09/29/2023
% Done:
100%
Estimated time:
Planned Due Date:
Description
27/09/2023 & 29/09/2023
Supported the team members in fixing errors in the demo application code
Started initial works of PMP
Updated by Nisha Balakrishnan almost 3 years ago
- Tracker changed from Module to Activity
Updated by Nisha Balakrishnan almost 3 years ago
- Subject changed from Hands on & Code Famalirisation - week 3 to Hands on & Code Famalirisation - Initial Setup - Week 3
Updated by Nisha Balakrishnan over 2 years ago
- Status changed from New to Closed